Estimate Activity Duration sis the process of estimating the number of work period sto complete indivities with estimated  resources.The tools and technques is not including( ).

单选题
Estimate Activity Duration sis the process of estimating the number of work period sto complete indivities with estimated  resources.The tools and technques is not including( ).

Aexpert judgment

Banalogous estimating

Crequirements trace ability matrix

Dthree-point estimating